EXTRACONTRACTUALLY LIABLE

Respect to a third party when carrying out a mandate

Genevieve Forget, lawyer


Is a professional who receives a mandate and commits a fault when executing this mandate accountable only to the person who engaged hisher services? The answer is no. The professional may, in fact, be ordered to pay damages to the third party affected by the poor execution of the mandate and even sued.

 

This was the case in the matter of 3979687 Canada inc. v. Consultants LBCD inc. (JE 2010-664).

 

A company mandated an engineer from the LBCD firm to carry out soil analyses to determine whether or not a lot was contaminated. In 1996, a report was drafted and submitted to the company, concluding that the land was contaminated and that the rehabilitation process was undertaken in keeping with the requirements of the Ministère de l’Environnement. In 2003, the company wanted to sell the land and mandated the same firm to update the report, which was then submitted to the promising buyer, 3979687 Canada inc. The report stated that the contamination was minimal and superficial and could easily be remediated when digging the foundations. The sale was closed.

 

However, the contamination was extensive, and the new owner incurred some $200,000 in decontamination costs.

 

The owner therefore launched a suit against the engineering firm.

 

The firm was found liable by a Superior Court judge, who considered that the buyer had decided to purchase the lot only once it had received the certification that it was decontaminated. Because the firm’s guarantee caused the damages, it was ordered to reimburse the decontamination costs. 

 

LAW COLUMN 01/2012

Can work carried out for speculative purposes lead to a legal construction hypothec?

Excavation contractors and especially firms that carry out earthwork and levelling must therefore be aware of the context in which their services are engaged.

Read more...

Get a copy of the bond!

A. Électrique inc. has just been awarded the largest contract in its history from general contractor Miserly Construction. Upon signing the contract, Miserly insisted on including a clause by which André waived his right to file a legal construction hypothec in exchange for a bond guaranteeing the material and labour provided by A. Électrique inc. Thrilled with the new contract, André neglected to obtain a copy of the bond when signing the contract...

Read more...

Archives...

LATEST NEWS

January 2012

Training

Responsibilities of municipalities and governments - waterways

Read more...

December 2011

PFD welcomes new attorneys

Read more...

December 2011

Swearing in

Read more...

All the news...

 

© Prévost Fortin D’Aoust 2012, All Rights Reserved - Design RED l'agence

création web montréal

design web montréal